Ana səhifəProjectsFinished projectsGuba-Gonaqkend Road

"Pile Works Under the Bridge Foundations at Quba-Qonaqkənd Construction of Concrete Structure Bridge Construction of Bridges on the Highway"

"General Description of Work within the Project:


Pile Works Under the Bridge Foundations

Construction of Concrete Structure Bridge

Detailed Description of Main Works:


Total Concrete Works: 3132 m³

Total Reinforcement Works: 626.4 tons

Railing: 317 m"