Construction of New Runways at Z. Tagiyev Military Base and Airfield



Excavation and Profiling: Excavation and profiling of runways, aprons, and internal roads; construction of the roadbed and preparation of the subbase layer up to the top layer of the project.

Excavation and Profiling of Runways, Aprons, and Internal Roads:

Removal and transport of concrete blocks: 71,000 tons

Excavation and transport of soil: 480,000 m³

Compaction with fill material: 170,000 m³